South Cluster construction work continues over the summer
The construction work on the South Cluster is going ahead throughout the summer. See the photo's and the video below!
The middle building has now been demolished (see the video), marking the end of the demolition phase – which means that the real construction phase has begun. The concrete floor for the first storey of the new building has been poured and new concrete walls are in place.
At present, we are waiting for the large crane to be installed, so that elements like the steel framework of the roof, the prefab stairs and the wood skeleton of the walls can be constructed.
The photographs show the new concrete floor, the shuttering for the new concrete walls, the current situation in the large courtyard and the upper storeys.